Residential – RS |
Rate (Includes FCA) |
Fuel Cost
Adjustment(FCA) |
|
Customer Charge |
$12.23 |
|
|
Energy Charge |
|
|
| |
First 800 kWh |
8.811¢ per kWh |
1.722¢ |
| |
Additional kWh |
7.496¢ per kWh |
1.722¢ |
| |
|
|
|
| |
|
GSA 1 – Less than 50 kW and 15,000 kWh |
|
Customer Charge |
$19.48 |
|
| |
Energy Charge |
|
|
| |
First 900 kWh |
9.598¢ per kWh |
1.690¢ |
| |
Additional kWh |
8.460¢ per kWh |
1.690¢ |
| |
|
|
|
|
GSA 2 – Greater than 50 kW but not more than 1,000 kW or energy exceeds 15,000 kWh |
| |
|
Customer Charge |
$79.36 |
|
|
Energy Charge |
|
|
| |
First 15,000 kWh |
8.460¢ per kWh |
1.690¢ |
| |
Additional kWh |
5.080¢ per kWh |
1.654¢ |
|
Demand Charge |
|
|
| |
First 50 kW |
no charge |
|
| |
Excess over 50 kW |
$12.31 per kW |
|
| |
|
|
|
|
GSA 3 – Greater than 1,000 kW+ |
|
Customer Charge |
$288.57 |
|
|
Energy Charge |
|
|
| |
All kWh |
5.314¢ per kWh |
1.654¢ |
|
Demand Charge |
|
|
| |
First 1,000 kW |
$13.30 per kW |
|
| |
Excess over 1,000 kW |
|
|
| |
not to exceed 5,000 kW |
$ 9.18per kW |
|
| |
|
|
|
| *Incorporates adjustments set out in October 2003 Adjustment Addendum (Environmental Adjustment), October 2009 Adjustment Addendum and Fuel Cost Adjustment effective February 2012 |
|
| |
+Eligible for Small Manufacturing Credit if Standard Industrial Classification (SIC) code between 20 and 39 |
|
| |
|
|